Maine environmental board delays power line forest plan again

Maine environmental board delays power line forest plan again
100%

Maine Board of Environmental Protection Sends NECEC Conservation Plan Back for Revisions

August 30, 2026 – Augusta

The Maine Board of Environmental Protection (BEP) postponed a final decision on the 50,000‑acre conservation plan that was supposed to accompany the New England Clean Energy Connect (NECEC) transmission line, returning the proposal to state staff for further revisions. In a 5‑1 vote, the board cited several shortcomings in the latest draft, including a “10,000‑acre no‑cut sanctuary,” a ban on harvesting forest stands over 100 years old and a shift from measuring tree health by height to width and total wood.

Board Chairman Robert Duchesne said the panel would “put on a bow on it and send it back,” underscoring a continuing clash between the state’s desire to expedite the power line and environmental groups’ concerns about forest preservation.

The Transmission Line and the Conservation Plan

NECEC, a $950 million project owned by Central Maine Power’s parent company Avangrid, carries 1,200 megawatts of Canadian hydropower to Massachusetts via a 54‑mile, 150‑foot‑wide corridor that cuts across commercial forest between the Quebec border and The Forks Plantation. The line began commercial operations in January, but its completion hinges on a conservation plan that the BEP has ordered the state to develop.

The original proposal, presented in 2025, linked the line’s right‑of‑way to a landscape‑scale easement that would conserve over 400,000 acres of adjacent protected wilderness. NECEC Transmission LLC, through its attorney Lisa Gilbreath, argued that the plan was unprecedented in its scope and would allow Weyerhaeuser—one of Maine’s largest commercial timber owners—to clear‑cut set‑aside land under a “shifting mosaic” logging schedule that was supposed to guarantee that half of the conserved acres would contain 50‑foot‑tall trees by 2065.

Environmental groups—including the Appalachian Mountain Club, the Natural Resources Council of Maine, Maine Audubon and Trout Unlimited—challenged that arrangement, arguing that the 50‑foot benchmark represented mid‑aged “pole” stands rather than mature forest. They said the plan would leave the corridor fragmented and unable to support species that rely on older, multi‑layered trees and snags.

In September, the BEP sided with the environmental groups and ordered a new plan that would allow a larger portion of the 50,000 acres to mature and remain forested for an extended period. The board’s most recent draft, however, went “too far,” according to BEP members, by expanding the no‑cut zone and tightening harvesting restrictions.

Legal and Ecological Tensions

NECEC’s attorney, Gilbreath, told the board that it was unclear whether Weyerhaeuser could meet the new requirements. “They moved the goalposts,” she said. “The new plan targets late successional old growth, not mature forest, substitutes preservation for conservation, and it gives up a bird in hand for a proposal no one has shown to be feasible. The appellants keep asking for more.” Gilbreath urged a return to the original plan, which she said would eventually allow half of the conserved woods to reach maturity.

The debate reflects broader questions about what constitutes a mature forest in Maine’s commercial timberlands. Experts cited that native trees can reach 50 feet in 30 to 40 years, a growth rate that, while impressive, does not yield the structural complexity required by wildlife such as the pine marten, fishers, and black bears. Ecologists warned that the plan’s emphasis on tree height would miss critical habitat features like large denning hollows and standing dead snags.

Next Steps

The BEP’s decision to send the plan back does not affect the operation of the NECEC line, which will continue to transmit power. However, the delay may prolong legal disputes over the corridor’s environmental impact. State staff will revise the proposal to address the board’s concerns, and the BEP will consider the updated plan in a future vote.

For residents of the region, the outcome will determine how much of the 54‑mile corridor remains a mature forest and whether the line’s environmental footprint can be adequately mitigated. The board’s action underscores the state’s commitment to balancing energy infrastructure with conservation priorities, even as it navigates complex legal and ecological challenges.

Author

Maine News Now

Maine News Now

Related Stories

South Portland board opts not to alter elementary school districts
local5 hours ago

South Portland board opts not to alter elementary school districts

Portland councilor wants state law changed to give cities more control over speed limits
local8 hours ago

Portland councilor wants state law changed to give cities more control over speed limits

Planned legislation would name new bridge linking Topsham and Brunswick  | Column
local10 hours ago

Planned legislation would name new bridge linking Topsham and Brunswick | Column